WTC Construction Update, December 2011

WTC Construction Update, December 2011

Dec 12, 2011
By By: LMCCC |

4 World Trade Center 

Steel erection is progress on the 57th floor. Concrete core walls are complete up to the 50th Floor, with concrete on metal deck complete to the 53rd floor. Curtain wall installation complete to 38th floor (except hoist areas and tower crane 3 areas, which are complete to 32nd floor). 

3 World Trade Center 

Concrete core and concrete slab work continue to progress on schedule. Concrete in the west core walls has been placed up to level 3, and the majority of the B1 level concrete slab has been poured. Jumping operations for the east tower crane are expected to occur within the next month.

2 Work Trade Center 

The major below grade concrete superstructure elements are nearing completion, with the erection of the ground floor deck in progress. Installation of the PDC’s (Power Distribution Centers) has begun and will continue into the early part 1Q 2012. 

1 World Trade Center 

Structural Steel erection is currently at the 90th floor. Floor slabs have been cast through the 80th floor and core shear walls are up to the 79th floor. Curtain wall installation is complete up to the 63rd floor.

9/11 Memorial Museum 

Electrical, Mechanical, Fire Protection, and IT work continues in the Pavilion and underground museum. The carpentry contractor is installing sheetrock at the west side of the 2nd floor of the Pavilion, and has also begun to frame out the interior ceiling.  

Terms of Use

Copyright License

Use of this Website is subject to the terms of this disclaimer and by using the Website, you agree to these terms. Silverstein Properties, Inc. ("Silverstein") publishes this Website solely for general informational purposes and nothing herein is intended to be an offer of property, or leasehold or goods or services or employment or a representation as to property, or leasehold or goods or services or employment that will be provided to any person. Silverstein obtains some of the information on the Website from third parties and makes reasonable efforts to provide accurate information on the website. However, it cannot guarantee its accuracy and under no circumstances will it be responsible for inaccuracies whether in material provided by Silverstein or obtained from third parties. The information contained herein may change without notice. The information contained herein will only be considered a representation of Silverstein if repeated in a final contract signed by an authorized Silverstein representative.

Disclaimer

Silverstein Properties, Inc. grants to you a limited non-exclusive, non-transferable license to view, copy and print the material on this web site (other than the design or layout of this Website) for your non-commercial or personal use only. All copies that you make must retain all copyright and other notices that are on this Website. Otherwise, you may not use, distribute, sell, modify, transmit, revise, reverse engineer, republish, post or create derivative works of the material on this Website without Silverstein Properties, Inc.'s prior written permission in each instance.

© Silverstein Properties, Inc., all rights reserved except as expressly provided elsewhere on this Website.